New HS Construction Update
by rknelson

Read this blog and check back frequently to track the progress on the construction of our new high school building.
Construction sign

February 13, 2009
Moving day has finally arrived! The school is finished, except for the gym, and so we are moving in and classes will begin in the new facility Mon., Feb. 16. The side practice goals need to be relocated in the gym and the floor needs to be laid. Work is continuing on the track as well.
Classroom with computers upFront of the buildingFront reception areaGym entry wayLibraryHallwayCourtyard with treesGym logoFront view of school with grass

December 5, 2008
The school is really taking shape now. We'll be moving in as soon as everything is finished! The classrooms are getting finishing touches. The doors are being put in, and floor coverings are being laid. It's getting exciting!
Classroom
Front doors
Gym
Exterior view

September 26, 2008
Progress is continuing on the new school. In fact, about the only delay is waiting on bricklayers. The pics below show the inside of the cafetorium, which is adjacent to the gym, one of the classrooms, and some of the network cables being pulled for all the computers in the school. The parking lot has been poured behind the football stadium and work continues on the track.
CourtyardGym wall inside cafetoriumCafetorium - stage viewClassroomNetwork cablesExterior view - parking lot

August 11, 2008
The new school is really taking shape now. All of the foundation has been poured and all areas have been framed. Sheetrock will be applied soon to the interior walls, and the brick has finally arrived for the exterior. The courtyard was initially off by 14" but it has now been ripped out and repoured. Everything is still on schedule.
Courtyard
Cafetorium
Front entrance

July 1, 2008
Progress is continuing throughout the hot summer months--right on schedule. Almost all of the school and gym is framed and the track has been dug.
Gym
South wing
Track

May 30 - June 6, 2008
By the end of May we finally have the gym almost completely framed and the concrete slab for the north wing poured. A week later the north wing is being framed.
Framing of gym
North wing concrete
Framing of north wing

May 2, 2008
The beginning of May finally brought some visible construction of our new facility! Three beams for the gymnasium went up in the air on May 1 followed by the pouring of some of the foundation on May 2. Dirt work on the track should begin next week.
First three standing beams
Gym foundation

April 11, 2008
All 263 piers are finally in the ground, and now grade beams are being dug and poured. Plumbing should start next week (weather cooperating!). A bid for the track was accepted this week as well and construction of the track should begin soon.

March 17, 2008
After quite a bit of rain and snow in recent weeks, construction workers were finally able to start drilling piers today. In all they will place 263 piers five to 22 feet under the slab. Also, workers started cutting the parking lot to hook up water and sewer for the new building.
Drilling piers
Cutting parking lot

Feb. 18, 2008
Construction began around mid-January 2008. A month later we're still in the preliminary stages (dirt work) to prepare the foundation.
Dirt work

High School

<  February 2008  >
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29    

Search

Categories


Archives

Misc


RSS 2.0 Feed